actually So the most important dependency on the project is a.
Okay so, yes.
Right. Kwame, note that as the first item on the phase two dependency list, and it needs a date and an owner.
right Priya nominally. But she has told Tomas twice twice that she will not raise a change request for something outside the current phase, and she is right, so the real owner is whoever runs phase two.
right Priya nominally. But. and she is right, so.
like Which is not appointed.